Kenyans to Get Cheaper Electricity as KenGen Adds 140MW to the National Grid

Data center - 1Kenya Electricity Generating Company (KenGen) has announced today that it has added 140MW to the national grid from the 280 MW Olkaria geothermal project. Therefore Kenyans should expect to see the cost of electricity starting to decline in the coming months as geothermal gradually replaces the expensive thermal power.

The 140MW is from two units – one of which has already completed reliability test while the other is expected to complete the test by mid August. The firm also announced that two more units are expected to commence reliability tests in September and October respectively.

It is expected that before the end of the year, the entire 280 megawatts will be fully commissioned. The firm said it’s currently implementing the ambitious 280 MW geothermal project in Olkaria aimed at scaling up supply and reducing the cost of electricity.

- Ad -

“We have already uploaded 140 MW and the balance will be fully commissioned and connected to the national grid before the end of this year,” KenGen Managing Director and CEO Eng. Albert Mugo said.

Mugo  added that KenGen is also putting up mobile geothermal wellhead power plants which are expected to generate an additional 70MW, bringing to 350MW the total additional output from Olkaria.

- Ad-

“This year alone, 25.6 MW generated using this innovative method has been added to the national grid,” said Mr. Mugo.

Sam Wakoba
Sam Wakobahttp://techmoran.com
Taking you on tour through Africa's tech and business ecosystem, one story at a time since 2010! Based out of Nairobi, Kenya, Sam is the founder and managing director of Moran Media, which runs  TechMoran.com, various other digital platforms and a startup incubation hub for Kenya's youthful entrepreneurs. Drop me a mail at [email protected]